must we adjudicate?

 

construction child

 

You may already be aware that in the recent case of DGT Steel and Cladding –v– Cubbitt Building and Interiors, HHJ Peter Coulson QC helpfully clarified the law covering contractually binding dispute resolution clauses.

 

The court will generally stay court proceedings, started in breach of a contract that says that disputes shall be referred to adjudication or some other form of alternative dispute resolution first. The party resisting a stay of court proceedings must show why the agreement in the contract to adjudicate, mediate or go down an alternative ADR route should not be enforced.

 

It's important to note that the Construction Act 1996 gives parties to a construction contract the right to refer disputes to adjudication; but there is no obligation to do so. With most construction contracts, there would be nothing expressly preventing one party commencing adjudication and the other immediately commencing court proceedings. However, even if the adjudication provisions in contract are not mandatory, the court still has discretion. HHJ Coulson’s view was that a stay would often be appropriate, even if the court was only dealing with a right to adjudicate.

 

Otherwise one or other party would be denied its right to have the dispute adjudicated. If appropriate pre-action steps had not been taken (in compliance with the pre-action protocol) a stay pending the outcome of the adjudication would most likely find favour with the court. Furthermore, the judge said that in circumstances where the dispute involved the valuation of an account, an experienced construction professional, particularly a quantity surveyor, could provide a better tribunal for resolving the dispute than the court.

 

So it seems that the only difference between an adjudication agreement that requires disputes to be referred to adjudication, as opposed to a right to adjudicate by virtue of Section 108, is that if the recourse to adjudication is mandatory, the court would be more willing to exercise its discretion in favour of a stay. There might however be good reasons why a court would order a stay of proceedings whilst the adjudication concluded, even where there were no obligation in the contract to adjudicate.

 

Generally, courts are reluctant to interfere with the adjudication process and the jurisdiction of adjudicators.

 

For further information please contact Richard Wade on 01865 254244 or email richard.wade@bllaw.co.uk

in Issue 6, February 2008...
 

is contractor's cash flow king under the Construction Act?

----

when fixed price means fixed price

----

must we adjudicate?

----

CIS and CDM: the regulatory double whammy of 2007

----

site waste management plans

----

the new Part 36: no payment required!

----

BL Resolve comes of age...

----

Vigil

----

 
download as a pdf
Adobe download icon
 
visit our archive