construction and development law update - October 2011

new Construction Act takes effect from 1 October 2011

The most important legislative change to the construction industry in 13 years.  On 1 October 2011 the new Construction Act (containing Part 8 of the Local Democracy, Economic Development and Construction Act) comes into force bringing with it substantial changes to mechanisms governing payment along with less significant changes to provisions for adjudication.  In addition, from 1 October onwards, construction contracts will no longer need to be in writing (or evidenced in writing) in order to be covered by the legislation. 

substantial changes to payment mechanisms

The new Construction Act introduces a principle whereby a payer must pay the "notified sum" on or before the final date of payment.  Provisions for the issue of payment notices are provided in new Sections 110A and Section 110B and introduce the concept that a payment notice may be issued by either the payer or the payee.  The rationale behind the change is that the parties further down the contractual supply chain may now take the initiative in terms of driving cash flow.  If a payer is slow to issue a payment notice the payee may step in or effectively "trump" the payer's position by issuing its own notice.  This scenario presents several traps for the unwary since the payer will be bound to pay the sum covered by the "payee notice", unless it is astute enough to issue its own counter notice.

The new Act preserves the concept of "due" and "final" dates for payment and payment notices must be issued no later than five days after the "due" date.

Under the old (1996) Act the payer still had the option to withhold money from any sums otherwise due.  That concept remains under the new Act although the old style "withholding" notices have been replaced by new style "pay less" notices.  As previously, a "pay less" notice (in other words a notification from the payer that it intends to pay a sum less than that which has fallen due) must be issued no later than the end of "prescribed period" (which can be agreed by the parties to the contract) which must end before the final date for payment. 

A final, significant, amendment to the payment provisions is contained in Sub-Section 110(1A) which stipulates that any term requiring payment to be conditional on performance of obligations under another contract will fall foul of the requirement to have an adequate payment mechanism.  Consequently, provisions that state that payment of, for example, a final balance of retention due to a sub-contractor is dependent upon the issue of a certificate under a higher contract in the chain will be rendered ineffective.

amendments to adjudication provisions

There are minor changes made in relation to the timetable for adjudication and to allow an adjudicator to correct minor errors in his or her decision.  However the main change in relation to adjudication is the amendment to the provisions on costs and, in particular, the final nail in the coffin of "Tolent" clauses.  These are clauses which require a referring party to pay the costs of the adjudication and/or the adjudicator's fees.  Such terms are now ineffective under the new Act.

For further information, please contact Richard Wade, head of Blake Lapthorn solicitors' Construction and Development group on richard.wade@bllaw.co.uk or call 01865 254244.