is contractor's cash flow king under the Construction Act?

According to the House of Lords in Melville Dundas Ltd
–v– George Wimpey (2007), the answer is no. In essence, provided
that the contract allows, even an employer that has not served a
valid withholding notice can withhold payments that are already due
to an insolvent contractor.
One of the aims of the 1996 Construction Act is to safeguard
contractors' cash-flow. An element of this is that the employer
must issue a valid notice before attempting to withhold any payment
that has fallen "due". The contract used in this case provided for
termination and withholding of payments should an
insolvency event take place. There was a clear tension between
the Act and the contract. The House of Lords decided, under the
insolvency provisions, that the contract allowed the employer under
contract (Wimpey) to avoid paying the “due” instalment. They
rejected Melville Dundas' argument that once a payment was due it
could not become "undue". The wording covered "any further payment"
and all five judges held that the insolvent contractor ceased to be
entitled to any further payment, whether due or not.
The judges had more difficulty with the issue of whether Wimpey
could withhold payment based on the contractual position, as they
had not issued a valid withholding notice under the Act.
By a slim majority they held that the Act must be interpreted in
a way that was compatible with the insolvency provisions in the
contract. The court also found that it could not have been
Parliament's intention to deny employers protection under
established insolvency provisions if there was no way they could
serve a notice (given that the contractor became insolvent after
the due date for the payment). They concluded that Parliament
would rather have included an express provision to cover insolvency
issues in the Act.
Consequently, contractors no longer have a clear case if the
employer fails to issue a withholding notice. It is possible that
this decision lets employers withhold payments on grounds that
would have been impossible to argue before a payment deadline. This
may even extend to defects that arise after a withholding notice is
due, allowing the employer to retain the cost of fixing the
problem. While this is conjecture, contractors and employers (and
indeed insolvency practitioners) must note that termination clauses
like those in the JCT forms are not overruled by the Act.
For further information please contact Richard Wade on 01865
254244 or email richard.wade@bllaw.co.uk
|