side agreements that vary contracts may not necessarily discharge a surety's liability under a bond

In the recent case of Hackney Empire v Aviva Insurance UK Ltd [2011] (TCC), Edwards-Stuart J in the Technology and Construction Court redefined current case law and held that a side agreement and advance payments on account of a loss claim did not discharge the surety’s liability under a bond. As the law stood, commercial agreements with a bond or guarantee in place were in danger of discharging that bond or guarantee should any of the underlying obligations be varied. 

the facts of the case

Hackney Empire Ltd (“Hackney”) contracted Sunley Turriff Construction Ltd (“Sunley”) to carry out extensive renovations on the Hackney Empire Theatre in East London.  Shortly after the work started, Aviva stepped in to provide a bond for Sunley in favour of Hackney to secure due performance of Sunley’s obligations under the contract.  During building works Sunley made numerous claims and so in December 2002 Hackney agreed to pay £500,000 on account of the claims in return for a revised earlier completion date. Following a side agreement being entered into, Hackney payed Sunley another £250,000 in February 2003. In July 2003, prior to the building works being completed, Sunley went into administration. Hackney sued Aviva to recover the £750,000 paid in advance to Sunley.

Aviva claimed that the contract under which it had issued a bond to Sunley had been varied by the side agreement without their knowledge or consent, they were therefore discharged from the bond. Hackney claimed the side agreement only varied the contract in ways in which were acceptable under that contract.

decision

Edwards-Stuart J rejected Aviva’s argument and held that although the side agreement varied the contract, it did so in ways that fell within exceptions to the rule in the leading case law of Holme v Brunskill and General Steam Navigation v Rolt.  The court concluded that:

  • under Holme v Brunskill, an alteration in terms of the principal contract will discharge the surety unless it is self-evident, without enquiry, that the alteration is insignificant or non-prejudicial
  • under General Steam Navigation v Rolt, conduct that does not vary the principal contract must be prima facie prejudicial in order to discharge the surety.

The Court held that the payment of £500,000 did not amount to material alteration of the building contract and so the rule in Holme v Brunskill did not apply. The payment of £250,000, although it varied the contract through the side agreement, was not prima facie prejudicial to Aviva and in fact was beneficial to them.   Again, the rule in Holme v Brunskill did not apply and for the same reasons neither did the rule in General Steam Navigation v Rolt

future

Looking to the effects this decision will have in the future, we will need to be certain, when obtaining a bond that the contract under which it is obtained provides express wording to ensure it is not invalidated by variations.  Unless this wording is included it may be that insurers or providers of the bond can succeed in arguing that variations to the terms of a contract will render the contract discharged.

For further information on the articles contained in this bulletin, please contact Kath Shimmin, head of Blake Lapthorn's Finance group on kath.shimmin@bllaw.co.uk or call 023 8085 7081.